FOCI Cruise Planning Documents


 
TITLE
PURPOSE
PERSONNEL
 DUE DATE
Project Description Form PDF: Anticipates science plans for the upcoming season PIs submit to FOCI Coordinator July
Field Operations Schedule Lists cruises, dates, ports, operations, personnel.  Go to "Cruise Calendar" for additional information. FC and FOLs create draft September
Cruise Overview Preliminary document summarizing operations, special needs CS submits to FLO and FOLs December
Sample Request Form and SRF purpose/abbreviation key SRF: describes samples to be collected and processing requirements; Rich Text Format PIs submit to CS 120 days before cruise
Chemical Inventory ChemI: pre- and post-cruise; lists all chemicals to be used by a research component during a cruise, and how they were used and what portions remain after a cruise, see "HAZMAT" section for additional guidance. PIs submit to CS 120 days before cruise
Material Safety Data Sheets MSDS: provides detailed information for each chemical PIs submit to CS 120 days before cruise
Cruise Instructions CI: draft and final; list logistics and operations for cruise.  Go to "Writing Cruise Instructions" for additional guidance. CS submits to FOLs and FLO 95 days before cruise
Chemical Disposal Plan Instructs personnel when owner does not personally load and unload.  Go to "HAZMAT" section for additional guidance. PS submits to CS 100 days before cruise
Chemical Transfer and Storage Form Provides for temporary storage of chemicals and transfer of chemicals to new responsible party or vessel.  Go to "HAZMAT" section for additional guidance. PS submits to other responsible party 45 days before loading
Ship Operations Evaluation Form  Evaluation of ship performance  CS submits to the FLO at the laboratory No later than 25 days after the cruise
Cruise Report CR: a compilation of scientific accomplishments during cruise.  Go to "Writing Cruise Reports" for additional guidance. CS submits to vessel captain, FOLs, FC and FDC Within 30 days after cruise