EcoFOCI Mooring Hardware RequestContract Vessel (Bering & Chukchi Seas) |
| Updated: April 10, 2013 |
| 75 | 300 | 600 | ASL | RCM | temp. | temp. | AURAL | AWCP | PALS | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Approx. | Operation | Mooring | kHz | kHz | kHz | TAPS | Ice | Eco | ISUS | ISUS | SUNA | PCO2 | Micro | 9 ox/ | Sea | sensor | sensor | Sound Rec | Sound Rec | Sound Rec | rel. |
| Depth | ADCP | ADCP | ADCP | Buoy | Fluor. | (pmel) | (UAF) | (pmel) | Cat | turb/cond | Cat | SBE-39 | MTR | (MML) | (PSU) | (UW) | |||||
| Subsurface Moorings | |||||||||||||||||||||
| 72 | Rec/Deploy | 13BS-2C | 1 | 2 | 1 | 2 | 1 | 2 | 3 | 10 | 1 | ||||||||||
| 72 | Rec/Deploy | 13BSP-2B | 1 | 1 | 1 | 1 | 1 | ||||||||||||||
| 72 | Rec/Deploy | 13BS-4B | 1 | 3 | 1 | 5 | 10 | 1 | |||||||||||||
| 72 | Rec/Deploy | 13BSP-4B | 1 | 1 | 1 | ||||||||||||||||
| 70 | Rec/Deploy | 13BS-5A | 1 | 2 | 1 | 9 | 1 | ||||||||||||||
| 70 | Rec/Deploy | 13BSP-5A1 | 1 | 1 | 1 | 1 | 1 | ||||||||||||||
| 71 | Rec/Deploy | 13BS-8A | 1 | 2 | 1 | 8 | 1 | ||||||||||||||
| 71 | Redc/Deploy | 13BSP-8A1 | 1 | 1 | 1 | 1 | |||||||||||||||
| 43 | Deploy | 13CKP-1A | 1 | 1 | 1 | 1 | |||||||||||||||
| 42 | Rec/Deploy | 13CKP-2A | 1 | 1 | 1 | 1 | 1 | ||||||||||||||
| 43 | Deploy | 13CKP-5A | 1 | 1 | 1 | 1 | 1 | ||||||||||||||
| 43 | Deploy | 13CKP-6A | 1 | 1 | 1 | 1 | 1 | ||||||||||||||
| 43 | Deploy | 13CKP-7A | 1 | 1 | 1 | 1 | 1 | ||||||||||||||
| 43 | Deploy | 13CKP-8A | 1 | 1 | 1 | 1 | |||||||||||||||
| 1000 | Deploy | 13CKP-9A | 1 | 1 | 3 | 1 | |||||||||||||||
| 43 | Deploy | 13CKIP-1A | 1 | 1 | 1 | ||||||||||||||||
| 42 | Rec/Deploy | 13CKIP-2A | 1 | 1 | 1 | ||||||||||||||||
| 43 | Deploy | 13CKIP-5A | 1 | 1 | 1 | ||||||||||||||||
| 43 | Deploy | 13CKIP-6A | 1 | 1 | 1 | ||||||||||||||||
| 43 | Deploy | 13CKIP-7A | 1 | 1 | 1 | ||||||||||||||||
| 43 | Deploy | 13CKT-1A | 1 | 1 | 1 | ||||||||||||||||
| 42 | Rec/Deploy | 13CKT-2A | 1 | 1 | 1 | ||||||||||||||||
| 43 | Deploy | 13CKT-5A | 1 | 1 | 1 | ||||||||||||||||
| 43 | Deploy | 13CKT-6A | 1 | 1 | 1 | ||||||||||||||||
| 43 | Deploy | 13CKT-7A | 1 | 1 | 1 | ||||||||||||||||
| 43 | Deploy | 13CKT-8A | 1 | 1 | 1 | 1 | |||||||||||||||
| TOTAL | 1 | 7 | 3 | 6 | 5 | 9 | 4 | 2 | 1 | 1 | 16 | 10 | 11 | 25 | 20 | 4 | 3 | 2 | 26 | ||
| 1 | Cruise Information: Vessel contract TBD |
| 2 | Shipping Information:Tentatively scheduled to load in Seattle in early June 2013 [SUBJECT TO CHANGE] |
| 3 | Special Request: Include additional lengths of spare chain pieces: 3 @ 5m and 6 @ 1m |
| NOTE 1 | 13BSP-5A and 13BSP-8A were built on a previous order, and are stored waiting a cruise.. These have been moved from April cruise list to this June cruise. |